A Dry Place to Work

Yesterday we finished sheeting the ground floor joists and the basement walls. The only opening in the house is a three-by-three opening in the stairwell that we can climb into with a ladder. We’ve snapped exterior wall lines and stacked … Continue reading

Posted in Uncategorized | 1 Comment

Subfloor

Working seven days a week is not for me. I can make that statement with complete confidence. It’s getting harder to get out of bed every morning. Not mentally, but physically. Today we nearly finished laying the subfloor but my … Continue reading

Posted in Uncategorized | 1 Comment

First Day of Framing

Yesterday was our first day of framing and it went fairly well. The temperature held above freezing. I know this because of the mud we were wallowing in all day. There are still two large and deep patches of snow … Continue reading

Posted in Uncategorized | Leave a comment